dc.description.abstractThe U.S. Coast Guard upcoming acquisition of the Offshore Patrol Cutter (OPC) offers many opportunities to leverage recent procurement lessons to achieve the program's affordability requirement of $310 million per hull. We explore the question of how lessons learned from the National Security Cutter (NSC) and Fast Response Cutter (FRC) procurement programs were applied to the OPC acquisition strategy to achieve affordability. We examine procurement lessons addressing management reforms, best practices in competition, contract structure, multiyear procurement, requirements generation, and test and evaluation. We employ a cost estimation model developed by Jeffrey Lineberry and first advanced in his 2012 work Estimating Production Costs While Linking Combat Systems and Ship Design. We validate the Coast Guard's OPC cost requirement of $310 million per hull using notional design data. We further illustrate the impact that varying specific design characteristics (speed, personnel, and length/beam) have on ship production cost. Finally, we conclude that the U.S. Coast Guard has successfully incorporated lessons from the NSC and FRC procurement programs into the OPC acquisition strategy, and we present a trade-off analysis that program managers may use in future source selection processes.
dc.description.sponsorshipAcquisition Research Program
dc.languageEnglish (United States)
dc.publisherAcquisition Research Program
dc.relation.ispartofseriesAcquisition Strategy
dc.relation.ispartofseriesNPS-AM-16-012
dc.subjectProcurement
dc.subjectAcquisition Strategy
dc.subjectAffordability
dc.subjectCost Estimation Model
dc.subjectShip Costs
dc.titleU.S. Coast Guard Cutter Procurement Lessons Impacts on the Offshore Patrol Cutter (OPC) Program Affordability
dc.typeTechnical Report
Appears in Collections:NPS Graduate Student Theses & Reports

Files in This Item:
File SizeFormat 
NPS-AM-16-012.pdf2.04 MBAdobe PDFView/Open


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.