Title: Enhancing the Enhanced Scenario-Based Method of Cost- Risk Analysis
Authors: Seth T. Hooper
Keywords: Cost-Risk Analysis
Actual Cost
Full-Rate Production
Weapons System Acquisitions Reform Act (WSARA)
Issue Date: 16-Nov-2011
Publisher: Acquisition Research Program
Citation: Published--Unlimited Distribution
Series/Report no.: Cost Risk Analysis
NPS-CE-11-177
Abstract: The current s-curve method of cost-risk analysis for major DoN acquisitions projects does not accurately estimate actual cost when the program reaches full-rate production. Another, sometimes more effective method of measuring cost risk, is the enhanced scenario-based method (eSBM) of risk analysis. The reason that cost estimations based on Milestone B costs are inaccurate is that little, if any, real information about the project is known at that point in the project. eSBM allows managers a less statistically tasking method of determining cost risk for a project, while still maintaining the requirements of the Weapons System Acquisitions Reform Act (WSARA) of 2009. In measuring the usefulness of eSBM, the key factors should focus on the acquisition strategy being used for the project and the time frame from Milestone B to later milestones. I hypothesized that different acquisition strategies will yield different levels of success in estimating cost risk for eSBM.
Description: Cost Estimating / Graduate Student Research
URI: https://dair.nps.edu/handle/123456789/2018
Appears in Collections:NPS Graduate Student Theses & Reports

Files in This Item:
File SizeFormat 
NPS-CE-11-177.pdf569.57 kBAdobe PDFView/Open


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.