Title: Section 809 Panel - Recommendation #53 - Permit the Initiation of all Production Rate Increases, Provided Congress has Appropriated Sufficient Funding
Other Titles: Section 809 Panel - Recommendation #53
Authors: Section 809 Panel
Keywords: Continuing Resolutions
Planning, Programming, Budgeting, and Execution (PPBE) Process
Section 809 Panel
Appropriations
Issue Date: 15-Jan-2019
Publisher: Section 809 Panel
Citation: Unlimited Distribution
Series/Report no.: Resource Allocation
SEC809-RSC-19-0015
Abstract: The continuing resolution restrictions on production rate increases, like new start restrictions, are harmful to the acquisition system. They disrupt the Department of Defense (DoD) ability to plan contracts strategically, raise costs due to vendors building risk into their pricing, and potentially prevent the deployment of needed capabilities to warfighters. Consider initiation of a DoD production rate increase to be automatically approved, provided certain criteria are met.
URI: https://dair.nps.edu/handle/123456789/3599
Appears in Collections:Section 809 Panel: Reports, Recommendations & Resource Library

Files in This Item:
File SizeFormat 
SEC809-RSC-19-0015.pdf98.65 kBAdobe PDFView/Open


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.